In its statement in March, İzdemir announced that the machinery and equipment assemblies were completed and cold tests were started while the work on the steel mill investment process was ongoing. In the statement made by the company today, it was stated that the cold tests have been completed and the hot test phase, which is planned to be passed by the end of the second quarter of 2024, has started.
In the official statement made by Izmir Demir Çelik Sanayi A.Ş. (Izdemir), “At the current stage of our company's steel mill investment process, cold tests have been completed and hot tests have started.
Developments regarding the steel mill capacity increase investment, which continues with determination, will be shared with the public separately.”