In a statement made to the Public Disclosure Platform, the Company informed about the current developments in the "Steel Mill Capacity Increase Investment" process.
In the statement made by İzdemir, it was stated that the company completed the assembly of machinery and equipment in the steel mill investment process and started cold tests. By the end of the second quarter of 2024, it is planned to start hot tests.
It was emphasized that the ongoing stages of the Steel Mill Capacity Increase Investment will be shared with the public. It is expected that future developments regarding this investment will be followed.